Acura of Honolulu

Honolulu, Hawaii

Architect of Record & Construction Management

The Redmont Group managed the Design and Build process for this project. With the Owner under severe time restraints, we approached this project as a Fast-Track build with construction beginning before the design was fully complete.

 
 

The team managed multiple review agencies including the City & County of Honolulu and Acura Corporate to review design, all while issuing design drawings in time for construction activities to stay on pace. The total project timeline was reduced from a typical period of 18 months to 6 months total and met the move-in date the Owner needed.

 
 

The Redmond team did a fantastic job of listening to and understanding the unique aspects of the project and translating the Acura Design Standards into a design that better met our needs while in a cost effective manner

- Eric Iversen | Director of Lithia